Consulting - Building in Turnau
What needs to be clarified before construction begins – the building authority can help
It is both sensible and cost-effective to contact the municipality before starting a planned construction project. During a free preliminary meeting or construction consultation, details and open questions can be discussed and clarified. Don't forget – since February 2020, a revised legal framework for both building and regional planning laws has been in place in Styria!
For the preliminary consultation, the following points are important:
-
Clarification of property ownership
-
Presentation of the planned construction (sketches, plans, photos of similar buildings, etc.)
-
Location of the planned building on the property
-
Suitability of the building site (zoning, utilities such as water, wastewater, electrical energy, load-bearing capacity of the ground, safety risks to neighboring buildings, protection from avalanches, flooding, groundwater, mudslides, rockfall, landslides, etc., suitable and legally secured access, soil permeability, permissible noise emissions, etc.)
-
Has a zoning plan been adopted for the property? – If yes, then building volume, building location, roof shapes, etc., are already specified.
-
Is there a construction obligation within a certain timeframe?
-
Are there any easements on the property?
What does the municipality do?
In the first step, the municipality checks the following questions:
-
Is the construction project "subject to approval," "subject to approval under a simplified procedure" (formerly "notification requirement"), or only "reportable" (formerly "not requiring a building permit")? For example, covered parking, outbuildings, fences.
-
Can construction take place on this site? (zoning, access, utility lines, water rights, other rights?)
-
Are the distances to neighboring properties in compliance with the building regulations?
-
Are neighboring rights affected?
What happens next?
The complete submission documents are processed by the municipality, and either a building negotiation is scheduled, or – in the simplified procedure – the legal neighbors sign the construction plan to give their approval.
If all legal conditions are met, a building permit decision will be issued depending on the category of the construction project. In the event of an appeal against this decision, the Styria State Administrative Court will make a ruling.
Advance registration for construction consultation is requested at the Turnau Municipal Office.